exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 535 discussion

Actual exam question from CompTIA's PK0-004
Question #: 535
Topic #: 1
[All PK0-004 Questions]

A project manager at a projectized organization is resource leveling the upcoming phase. The project manager notices one of the resources is assigned with 20% of allocation to a secondary project. This situation limits and jeopardizes the commitment date.
Which of the following should the project manager do NEXT?

  • A. Ask the functional manager to release the 20% of allocation from the secondary project.
  • B. Ask the sponsor to negotiate with the project manager from the secondary project.
  • C. Ask the PMO to assign additional resources.
  • D. Ask the project manager of the secondary project to release the resource.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MJVIS
2 years, 2 months ago
A projectized organization does not have functional managers in the traditional sense. In a projectized organization, all resources are assigned to projects full-time and report to the project manager. The project manager has complete control over the resources and is responsible for managing them, as well as managing the project itself. Therefore, in a projectized organization, there is no need for functional managers.
upvoted 1 times
...
MJVIS
2 years, 4 months ago
Selected Answer: B
The project sponsor is responsible for removing roadblocks.
upvoted 1 times
...
[Removed]
2 years, 10 months ago
Selected Answer: B
Prioritize Projects as per Strategic Business Objectives PMO plays a crucial role in this process and carries the following responsibilities: Ensure that the programs and portfolios are aligned to operational and strategic objectives Projects are selected and prioritized as per these business goals Enterprise resources are allocated and utilized as per business goals Design and track various program and portfolio performance KPIs
upvoted 2 times
...
devildog
3 years ago
If the PM is in a projectized environment, why would they consult the a functional manager?
upvoted 1 times
...
Treymb6
3 years, 1 month ago
The functional manager shouldn't really hold any decision making power in a projectized organization. Think the answer should be D, but it is definitely not A.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago