Question #: 173
Topic #: 1
[All PK0-004 Questions]

A project manager is creating the monthly report for top management. The project manager has collected the information below:

AC = 100 -

PV = 80 -

EV = 120 -
Based on this information, the CPI reflects which of the following about the project?

  • A. It is under budget.
  • B. It is over budget.
  • C. It is ahead of schedule.
  • D. It is behind schedule.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Explanation -
ג€The cost performance index (CPI) is calculated this way:
CPI = EV / ACג€
Excerpt From: Kim Heldman. ג€CompTIA Project+ Study Guide.ג€ iBooks.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ExamTopicsDiscussor
2 years, 5 months ago
Cost Performance Index = Earned Value/Actual Cost
upvoted 1 times
...
[Removed]
2 years, 9 months ago
Selected Answer: A
A. It’s performing under budget. CPI = EV/AC. 120/100=1.2.
upvoted 1 times
...
Jo1988
3 years, 2 months ago
Sorry my bad. CPI=1.2 means the project is under budget. So the answer is correct "it is under budget"
upvoted 2 times
...
Jo1988
3 years, 2 months ago
I believe the correct answer is "the project is over budget" since CPI=EV/AC in this case is CPI=120/100 which is 1.2. Hence, it's over budget.
upvoted 1 times
noblequest6
2 years, 10 months ago
No cause a CPI under 1 is over budget, whilst a CPI over 1 is under budget, and a CPI that equals 1 is on track
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago