A team member was assigned a new task during a meeting. The team member did not complete the task by the end of the phase, and the PM is looking for evidence to escalate the issue. Which of the following documents could help in this situation?
I chose A since, I was thinking that any prior issues with this team member, would have already been in the Issues Log, thus using that as the said "evidence"
Answer is correct. CompTIA Official guide has an example that aligns with this one pretty well. Page 312. PM assigns a task and issues arise so he goes to the issue log to look at historical entries for this task.
"From the earliest days of the project, David instituted the practice of using an issues log to track all matters in question or dispute in the project. "
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
papahawaii
2 years, 3 months agoHCEYLAN
2 years, 5 months agocatastrophie
3 years agocatastrophie
3 years agoboooliyooo
3 years, 1 month agozed01
3 years, 1 month ago