Question #: 201
Topic #: 1
[All PK0-004 Questions]

A daily standup Scrum meeting is BEST accomplished in a:

  • A. telephone conference.
  • B. group email.
  • C. face-to-face meeting.
  • D. video conference.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ExamTopics274
2 years, 8 months ago
Selected Answer: C
This is c without a shodow a
upvoted 1 times
...
ItsMeAgain99
2 years, 10 months ago
There is another question very similar to this one, though it mentions team members from various locations doing a stand up meeting. In that case, video conference is the best answer.
upvoted 1 times
...
some_specialist
3 years, 1 month ago
Selected Answer: C
The reason it's called a "stand up" in the first place, is because it's preferred to conduct this in person, while standing in a circle. The given answer is correct.
upvoted 3 times
...
boooliyooo
3 years, 4 months ago
Selected Answer: D
Lols. Video conference
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...