A technician is installing a variety of servers in a rack. Which of the following is the BEST course of action for the technician to take while loading the rack?
A.
Alternate the direction of the airflow
B.
Install the heaviest server at the bottom of the rack
B, Always load servers from the bottom up. This prevents servers from becoming top-heavy and tipping also we do not alternate the direction of the airflow because that would have already been setup on the room with airflow sensors
Not true and not from what I learned. normally heaviest equipment is Power supply units which take up 3U and two or three of those thing can be used. Servers should be installed in the middle to top of Server Rack. Something like this: KVM console, KVM Switch, Layer2 or 3 switch depending, servers, 2u space, then PSU.
A is clearly the joke answer.
Data centers have cold aisles and hot aisles. Cold air blows into the cold aisle for all the devices to pull through, exhausting out to the hot aisle.
Servers pull air through the front and push hot air out the back. Imagine you had two servers with alternating airflows... They'd just cycle hot air between each other!
1U spaces between servers is good if you have the space, but not essential. Putting heavy things at the top of an empty server is a recipe for disaster.
A is the correct answer, airflow is the first thing to be considered. New servers come with server rail, regardless the sizes, with the server rail and server lift, you only need to slide it out with no energy required. If you place the bigger one at the bottom and block the airflow, all the server on the rack will be overheating quickly.
It is essential to ensure to secure the rack to the floor. This prevents servers that are pulled forward on rails from overbalancing the rack and causing it to tip over. Floors must also be rated to properly support the weight of the servers, the rack, and any other IT equipment.
This question is far too vague to interpret without making a lot of assumptions, however, as a rule of thumb, one NEVER puts the heaviest object at the top of a vertical structure. Heavy objects should always be on the bottom in order of heaviest to lightest. I guess OSHA doesn't inspect data centers.
@Removed and Dion79: Keyword say the BEST course of action..
D is an optional implementation, while B is a standard implementation to prevent top-heavy rack.
Server Racks can be completely full with no space to accommodate. So leaving 1U space is not always the correct answer. It seems that its pointing to Hot & Cold aisles but the question almost seems its missing something.
You don't alternate airflow. Airflow always goes front to back.
UPS doesn't go at the top as it is probably the heaviest thing.
Leaving 1U gap is wasteful and not required. You should install everything from the bottom upwards and ensure the rack is not top heavy.
therefore correct answer is to install heaviest server at the bottom.
This section is not available anymore. Please use the main Exam Page.SK0-005 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Noms100
Highly Voted 2 years, 11 months agoDion79
2 years, 10 months agoskid40
Most Recent 7 months, 3 weeks agoRiseofashes
2 years agokadamske
2 years, 1 month agoPongsathorn
2 years, 6 months agonixonbii
2 years, 7 months agopaperburn
2 years, 7 months agoszl0144
2 years, 8 months agoi_bird
2 years, 9 months agoDion79
3 years agoPEsty93
3 years agodnc1981
3 years, 1 month ago