D. determine a mitigation strategy.
After accepting and assigning a positive risk (a risk that has the potential to bring benefits to a project), the risk owners have a responsibility to determine a mitigation strategy. This may involve identifying actions that can be taken to minimize the impact of the risk, or to maximize the probability that the risk will occur in a way that is beneficial to the project. The risk owners should also be responsible for updating the risk register to reflect the current status of the risk and any actions that have been taken to address it.
A. Maximizing the probability of a positive risk may be a goal of the risk mitigation strategy, but it is not the primary responsibility of the risk owners.
B. Updating the risk register is a responsibility of the risk owners, but it is not the only responsibility.
C. Minimizing the impact of a positive risk may be a goal of the risk mitigation strategy, but it is not the primary responsibility of the risk owners.
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
kmanb
2 years, 3 months agoManzer
2 years, 7 months agoBreakOff874
2 years, 9 months ago