A project manager has gathered time estimates for a new project's activities and is now ready to begin developing the schedule.
Which of the following would the project manager most likely do NEXT?

  • A. Create a WBS.
  • B. Determine predecessors and dependencies.
  • C. Determine the critical path.
  • D. Prioritize tasks.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Manzer
2 years, 9 months ago
Selected Answer: A
Steps to Developing a Project Schedule Step 1: Create a work breakdown structure. Step 2: Estimate durations. Step 3: Determine resources. Step 4: Identify predecessors. Step 5: Determine milestones. Step 6: Identify dependencies.
upvoted 1 times
all4one
2 years, 7 months ago
A is wrong because they have done step 2. So B is the correct answer.
upvoted 1 times
...
...
wisut
2 years, 12 months ago
Selected Answer: B
Wbs is done before estimate activity
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...