Question #: 744
Topic #: 1
[All PK0-004 Questions]

A project's purpose must be documented so the project manager can ensure the project stays within the parameters of what the client wants. Which of the following BEST covers this information?

  • A. Scope statement
  • B. Project charter
  • C. Status report
  • D. Project schedule
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
kmanb
2 years, 3 months ago
Selected Answer: B
Project Charter defines the purpose
upvoted 2 times
...
MJVIS
2 years, 4 months ago
Selected Answer: A
The answer is A- I am so confused with the correct answers. They don't make any sense.
upvoted 1 times
...
brvndvnwolf
2 years, 5 months ago
Selected Answer: A
A. scope statement
upvoted 1 times
...
CoinUmbrella
2 years, 6 months ago
Selected Answer: A
A project scope statement defines the project and what it does and does not need to accomplish.
upvoted 3 times
...
Sutokuto
2 years, 7 months ago
How is it not A??
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago