A recent change request was implemented with approval; however, it had an unforeseen negative impact on the critical path. Which of the following measures should be taken to ensure the project is not delayed?
A.
Evaluate the impact of the change.
B.
Execute the regression plan.
C.
Identify and document the root cause of the issue.
A. Evaluate the impact of the change is the measure that should be taken to ensure the project is not delayed when a change request was implemented with approval but had an unforeseen negative impact on the critical path.
When a change request is implemented and it has an unintended impact on the project, it is important to assess the impact of the change and determine what steps can be taken to minimize any delays or disruptions to the project schedule. This may involve reviewing the change request and the associated documentation, analyzing the impact of the change on the project schedule and other project deliverables, and identifying any risks or issues that may arise as a result of the change.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Sutokuto
Highly Voted 2 years, 7 months agokmanb
Most Recent 2 years, 4 months ago