Exam PK0-004 topic 1 question 838 discussion

Actual exam question from CompTIA's PK0-004
Question #: 838
Topic #: 1
[All PK0-004 Questions]

A stakeholder tells the project manager that a vendor was verbally aggressive during a meeting. Since the project is almost completed, the project manager decides to log and close the issue. Which of the following strategies does this represent?

  • A. Smoothing
  • B. Compromising
  • C. Forcing
  • D. Confronting
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Sutokuto
2 years, 8 months ago
Selected Answer: A
The correct answer is A.
upvoted 3 times
jksdbfb
2 years, 7 months ago
Would it not be forcing ?
upvoted 2 times
Sutokuto
2 years, 7 months ago
I interpreted it as the manager is pretending there isn't a problem. Forcing is a compelling answer. This exam sucks.
upvoted 4 times
...
kmanb
2 years, 4 months ago
In this scenario, the project manager decided not to use the forcing conflict resolution technique because it would not be the best approach for the situation. Forcing involves one party imposing their solution on the other party, without regard for their needs or concerns. While this technique can be effective in some situations, it may not be the best approach in this case for a few reasons: The vendor's aggressive behavior is not the main issue at hand. The project manager is more concerned with completing the project successfully, rather than addressing the vendor's behavior. The project is almost completed, and there may not be enough time to fully address the vendor's behavior. Forcing the vendor to change their behavior may not be practical or effective, especially if the project is almost completed and the vendor is no longer needed for the project. Overall, the smoothing technique may be more effective in this situation because it allows the project manager to focus on the goal of completing the project, while minimizing the impact of the vendor's behavior on the project.
upvoted 1 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel