The project manager for a multinational project is evaluating the option of scheduling face-to-face meetings during the release of a new system. The goal is to provide 24/7 coverage and quick responses to issues. Which of the following strategies is being applied?

  • A. Risk acceptance
  • B. Risk avoidance
  • C. Risk transference
  • D. Risk mitigation
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Sutokuto
Highly Voted 2 years, 8 months ago
Selected Answer: D
This is mitigation
upvoted 5 times
...
MJVIS
Most Recent 2 years, 5 months ago
Selected Answer: D
Mitigation- He is not avoiding the risk, which is the pre-selected answer.
upvoted 1 times
...
brvndvnwolf
2 years, 5 months ago
Selected Answer: D
D is the correct answer
upvoted 1 times
...
Chambone
2 years, 7 months ago
Mitigation
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago