exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 856 discussion

Actual exam question from CompTIA's PK0-004
Question #: 856
Topic #: 1
[All PK0-004 Questions]

Which of the following is the MOST likely trigger to update the project risk register?

  • A. An issue occurs.
  • B. A quality audit is passed.
  • C. A project milestone is completed.
  • D. A stakeholder initiates a change request.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
kmanb
2 years, 4 months ago
Selected Answer: A
The most likely trigger to update the project risk register is A. An issue occurs. The project risk register is a document that is used to track and manage risks throughout the life of a project. It typically includes a list of identified risks, along with information about the probability and impact of each risk, the risk response plan, and the current status of each risk. When an issue occurs – that is, when a risk event occurs and has a negative impact on the project – it is important to update the risk register to reflect the current status of the risk. This may involve revising the risk response plan, reassessing the probability and impact of the risk, and updating the status of the risk to reflect its current status.
upvoted 2 times
...
brvndvnwolf
2 years, 5 months ago
Selected Answer: A
An issue is def something you want to update the risk register
upvoted 1 times
...
Netlink
2 years, 6 months ago
Selected Answer: D
A stakeholder initiating a change request sounds like a RISK to me
upvoted 1 times
...
Sutokuto
2 years, 7 months ago
Selected Answer: D
See the question below this one
upvoted 1 times
boxv4
2 years, 7 months ago
The key words are "MOST likely." When an issue occurs you're going to update the risk registry to have an up-to-date log of these things. While the question after is specifically speaking about a change that will make project go over the allocated project, which in itself is a risk that will need to be logged and contact the appropriate people. I think the answer here is correct.
upvoted 3 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago