The most likely trigger to update the project risk register is A. An issue occurs.
The project risk register is a document that is used to track and manage risks throughout the life of a project. It typically includes a list of identified risks, along with information about the probability and impact of each risk, the risk response plan, and the current status of each risk. When an issue occurs – that is, when a risk event occurs and has a negative impact on the project – it is important to update the risk register to reflect the current status of the risk. This may involve revising the risk response plan, reassessing the probability and impact of the risk, and updating the status of the risk to reflect its current status.
The key words are "MOST likely." When an issue occurs you're going to update the risk registry to have an up-to-date log of these things. While the question after is specifically speaking about a change that will make project go over the allocated project, which in itself is a risk that will need to be logged and contact the appropriate people.
I think the answer here is correct.
upvoted 3 times
...
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
kmanb
2 years, 4 months agobrvndvnwolf
2 years, 5 months agoNetlink
2 years, 6 months agoSutokuto
2 years, 7 months agoboxv4
2 years, 7 months ago