exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 191 discussion

Actual exam question from CompTIA's PK0-004
Question #: 191
Topic #: 1
[All PK0-004 Questions]

Task B is not planned to start until Task A is completed. Task A is delayed and will not be completed on time. Starting Task B prior to Task A completing is an example of:

  • A. Managing change
  • B. Fast tracking
  • C. Rolling wave planning
  • D. Crashing
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Braniac
2 years, 8 months ago
given answer is correct, Rolling-wave planning is the process of project planning in waves as the project proceeds and later details become clearer Crashing is dedicating extra resources to meet a short deadline.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago