Task B is not planned to start until Task A is completed. Task A is delayed and will not be completed on time. Starting Task B prior to Task A completing is an example of:
given answer is correct,
Rolling-wave planning is the process of project planning in waves as the project proceeds and later details become clearer
Crashing is dedicating extra resources to meet a short deadline.