exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 791 discussion

Actual exam question from CompTIA's PK0-004
Question #: 791
Topic #: 1
[All PK0-004 Questions]

The AC plus ETC is known as:

  • A. earned value.
  • B. earned at completion.
  • C. budget at completion.
  • D. variance at completion.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
rpecana
2 years, 3 months ago
Selected Answer: B
Gents, This is B!
upvoted 1 times
...
Manzer
2 years, 7 months ago
Selected Answer: B
Estimate at Completion (EAC) The most common way to determine EAC is a “bottoms-up” formula where the actual costs (AC) are added to the forecasted remaining spending – the estimate to complete (ETC). EAC = actual costs (AC) + estimate to complete (ETC)
upvoted 2 times
Manzer
2 years, 7 months ago
So I guess none since that was not an option. Maybe it's a spelling mistake.
upvoted 1 times
bradseth
2 years, 3 months ago
what do you mean none? It's B EAC
upvoted 1 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago