Question #: 560
Topic #: 1
[All PK0-004 Questions]

A project is approaching its end when the project manager is informed that a deliverable is exceeding the upper noise limit set by the legislation of the country where it was implemented.
Which of the following constraints has MOST likely been overlooked?

  • A. Scope
  • B. Resources
  • C. Environment
  • D. Quality
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MJVIS
2 years, 5 months ago
Selected Answer: C
According to CompTIA, the following are the constraints on the project. Scope Schedule Cost Key Deliverables Requirements Quality Environment Resources
upvoted 1 times
...
Manzer
2 years, 7 months ago
Selected Answer: D
Environment is not a constraint of project manager scope and quality are
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.