Exam PK0-004 topic 1 question 584 discussion

Actual exam question from CompTIA's PK0-004
Question #: 584
Topic #: 1
[All PK0-004 Questions]

A project, which is nearing completion, is ahead of schedule and under budget. However, to improve quality to acceptable levels, the project will require additional time.
Which of the following BEST describes this scenario?

  • A. Score creep
  • B. Interactions between constraints
  • C. Constraint reprioritization
  • D. Change request
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
An example of interaction between constraints may occur when you have changes to scope that in turn impact the schedule and/or budget. Scope can change through the formal change control process or through scope creep. Perhaps your project sponsor has decided you need one more deliverable in order to satisfy the overall goals and objectives of the project. This is approved in a formal change request process. However, scope changes require schedule changes, and they often require budget changes as well. The interaction here is like a domino effect, and all the constraints should be reexamined to ensure that they still accurately reflect the conditions of the project.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
kmanb
2 years, 3 months ago
Selected Answer: D
Interactions between constraints refers to the ways in which the project constraints can influence one another. For example, if the project scope is increased, this may have an impact on the schedule and budget, as more work will need to be completed within the same time frame and budget. In this scenario, the project is ahead of schedule and under budget, but additional time is needed to improve the quality to acceptable levels. While the quality constraint may be interacting with the schedule and budget constraints, the team is not adjusting the priorities of the constraints in order to achieve the project objectives. Instead, the team is requesting a change to the project plan in order to allocate additional time for quality improvement, which would be considered a change request.
upvoted 1 times
...
Manzer
2 years, 7 months ago
Selected Answer: C
We're going to reprioritize quality
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago