A project team member states that the tasks identified in the project schedule for the week greatly exceed the number of available hours for the week.
Which of the following activities would have allowed the project manager to identify and correct this issue in advance?

  • A. Risk identification
  • B. Gate review
  • C. Resource allocation
  • D. Resource leveling
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MJVIS
2 years, 5 months ago
Selected Answer: D
Resource leveling is a resource management technique that can help teams better accommodate resource constraints and predict project timelines. It helps avoid poor project planning that often leads to last-minute delays, overworked team members, and cost overruns.
upvoted 1 times
...
Manzer
2 years, 7 months ago
Selected Answer: D
Resource leveling is used to analyze the schedule model. It allows you to readjust the work as appropriate so that people are not overly allocated. It is also used to address scheduling activities when critical resources are only available at certain times. Resource leveling is normally done after the critical path has
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago