A newly developed claims processing system will require users of the prior system to be trained to use the new system. During which of the following project phases should the training occur?

  • A. Closing
  • B. Executing
  • C. Planning
  • D. Monitoring and controlling
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Manzer
Highly Voted 2 years, 7 months ago
Selected Answer: A
Training is part of the closing phase
upvoted 5 times
...
MJVIS
Most Recent 2 years, 5 months ago
Selected Answer: A
Closing
upvoted 1 times
...
brvndvnwolf
2 years, 5 months ago
Selected Answer: A
A. Training is in the closing phase
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago