A change request has been submitted to change the construction material from cinder block to wood frame. Which of the following should be performed FIRST after the change has been approved by the sponsor?

  • A. Documentation update and review
  • B. Quality check
  • C. Team approval
  • D. Impact analysis
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
kmanb
2 years, 3 months ago
Selected Answer: D
D. Impact analysis should be performed FIRST after the change request has been approved by the sponsor.
upvoted 1 times
rpecana
2 years, 3 months ago
read the question carefully, my friend. Which of the following should be performed FIRST "AFTER" the change has been approved by the sponsor?
upvoted 1 times
...
...
Manzer
2 years, 7 months ago
Selected Answer: B
Quality check before document
upvoted 3 times
rpecana
2 years, 3 months ago
Quality check is before submitting the request, my friend not after.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.