D. a type of audit occurring during the project is an accurate description of a gate review.
A gate review is a formal review that is conducted at various stages of a project to assess the progress and viability of the project. It is typically conducted by a panel of experts who review the project documentation, assess the project's alignment with the organization's goals and objectives, and evaluate the project's risks and challenges. The purpose of a gate review is to ensure that the project is on track and that it is meeting the necessary standards of quality and performance.
A phase-gate review, also known as a governance-gate review, is a check point review of project
deliverables and performance that occurs at the end of each phase of a project where a management
review or sign-off may be required
While it is true that a gate review is a formal review that is conducted at various stages of a project, its purpose is not simply to review schedule changes. Rather, a gate review is a comprehensive assessment of the project that is intended to ensure that it is on track and meeting the necessary standards of quality and performance. It involves a review of the project documentation, an assessment of the project's alignment with the organization's goals and objectives, and an evaluation of the project's risks and challenges.
upvoted 1 times
...
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
kmanb
2 years, 4 months agobrvndvnwolf
2 years, 5 months agoManzer
2 years, 7 months agokmanb
2 years, 4 months ago