A gate review also is considered:

  • A. a method to make changes to resources.
  • B. an update to an incident response plan.
  • C. a checkpoint to review schedule changes.
  • D. a type of audit occurring during the project.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
kmanb
2 years, 4 months ago
Selected Answer: D
D. a type of audit occurring during the project is an accurate description of a gate review. A gate review is a formal review that is conducted at various stages of a project to assess the progress and viability of the project. It is typically conducted by a panel of experts who review the project documentation, assess the project's alignment with the organization's goals and objectives, and evaluate the project's risks and challenges. The purpose of a gate review is to ensure that the project is on track and that it is meeting the necessary standards of quality and performance.
upvoted 1 times
...
brvndvnwolf
2 years, 5 months ago
Selected Answer: C
C. key words: check point
upvoted 1 times
...
Manzer
2 years, 7 months ago
Selected Answer: C
A phase-gate review, also known as a governance-gate review, is a check point review of project deliverables and performance that occurs at the end of each phase of a project where a management review or sign-off may be required
upvoted 4 times
kmanb
2 years, 4 months ago
While it is true that a gate review is a formal review that is conducted at various stages of a project, its purpose is not simply to review schedule changes. Rather, a gate review is a comprehensive assessment of the project that is intended to ensure that it is on track and meeting the necessary standards of quality and performance. It involves a review of the project documentation, an assessment of the project's alignment with the organization's goals and objectives, and an evaluation of the project's risks and challenges.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago