exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 846 discussion

Actual exam question from CompTIA's PK0-004
Question #: 846
Topic #: 1
[All PK0-004 Questions]

A project team is assessing individual project risks by evaluating the probability for each one to occur, as well as the potential impact to project objectives using low, medium, and high values. The process the project team is using is known as:

  • A. risk response planning.
  • B. qualitative risk analysis.
  • C. quantitative risk analysis.
  • D. risk mitigation planning.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
brvndvnwolf
2 years, 7 months ago
Selected Answer: B
Answer is B - low, med, high
upvoted 1 times
...
CoinUmbrella
2 years, 8 months ago
Qualitative risk analysis is the process of determining the probability of occurrence and the impact of identified risks by using logical reasoning when numeric data is not readily available.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...