Exam PK0-004 topic 1 question 654 discussion

Actual exam question from CompTIA's PK0-004
Question #: 654
Topic #: 1
[All PK0-004 Questions]

Stakeholders often do not understand the hierarchy of roles and responsibilities on a project team. Which of the following could provide a visual representation?

  • A. Work breakdown structure
  • B. Milestone list
  • C. Organizational chart
  • D. Action items
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Reference:
https://www.wrike.com/project-management-guide/faq/what-is-work-breakdown-structure-in-project-management/

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MJVIS
2 years, 5 months ago
Selected Answer: C
Organizational chart
upvoted 1 times
...
brvndvnwolf
2 years, 5 months ago
Selected Answer: C
C. Organizational chart WBS has nothing to do with this
upvoted 1 times
...
all4one
2 years, 6 months ago
CCCCCC
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago