To control costs, project funding is being released under a waved approach. After passing each milestone, the project receives the next round of funding. Which of the following is hindered by this funding approach?
B. Crash schedule. A crash schedule involves compressing the schedule for a project as much as possible in order to complete it as quickly as possible. This typically involves adding additional resources or working overtime in order to speed up the project's progress. However, when funding is released under a waved approach, the project may not have access to the necessary resources or funding to implement a crash schedule. This is because the project only receives funding after passing each milestone, so it may not have the resources or funding available to add additional resources or work overtime to speed up the project's progress. Instead, the project may need to proceed at a slower pace, using the resources and funding that are available. This can hinder the project's ability to implement a crash schedule and may impact the project's overall timeline.
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
kmanb
2 years, 3 months agoall4one
2 years, 6 months agoall4one
2 years, 6 months ago