Question #: 824
Topic #: 1
[All PK0-004 Questions]

Which of the following is an attribute of a potential project?

  • A. Makes no changes to the work environment
  • B. Has no authoritative body
  • C. Comprises ongoing operational activities
  • D. Can be completed in one hour
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MJVIS
2 years, 2 months ago
Selected Answer: D
Can be completed in one hour. The project has a start and an end time.
upvoted 2 times
...
kmanb
2 years, 3 months ago
Selected Answer: D
A project is typically defined as a temporary endeavor undertaken to create a unique product, service, or result. One of the characteristics of a project is that it has a defined start and end date, and the work is typically time-limited. Therefore, it is possible for a project to be completed in a relatively short time frame, such as one hour.
upvoted 2 times
SEGA666
2 years, 2 months ago
https://work.chron.com/differences-between-shortterm-longterm-projects-11637.html
upvoted 1 times
...
...
all4one
2 years, 6 months ago
Operations are not projects. Weird question. Can someone help?
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago