exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 736 discussion

Actual exam question from CompTIA's PK0-004
Question #: 736
Topic #: 1
[All PK0-004 Questions]

A project sponsor requests an urgent change to the project scope that positively impacts the performance of the end product. Which of the following should the project manager do FIRST?

  • A. Ask the stakeholder to submit a change request.
  • B. Document the change and notify the stakeholders.
  • C. Change the project schedule with new estimates.
  • D. Notify the project team to prioritize the change.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MJVIS
2 years, 4 months ago
Selected Answer: A
Are we not going to follow the change control process here? Document the change Evaluate the impact Find an Alternate Solution Send the change to CCB for approval etc...
upvoted 2 times
...
HHHYY
2 years, 4 months ago
The first should document change.
upvoted 1 times
...
all4one
2 years, 6 months ago
Selected Answer: A
Shouldn't this be A?
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago