A project sponsor requests an urgent change to the project scope that positively impacts the performance of the end product. Which of the following should the project manager do FIRST?
A.
Ask the stakeholder to submit a change request.
B.
Document the change and notify the stakeholders.
C.
Change the project schedule with new estimates.
D.
Notify the project team to prioritize the change.
Are we not going to follow the change control process here?
Document the change
Evaluate the impact
Find an Alternate Solution
Send the change to CCB for approval etc...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
MJVIS
2 years, 4 months agoHHHYY
2 years, 4 months agoall4one
2 years, 6 months ago