Question #: 559
Topic #: 1
[All PK0-004 Questions]

Which of the following risk management activities identifies the severity of a risk event?

  • A. Quantification
  • B. Identification
  • C. Response
  • D. Mitigation
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MJVIS
2 years, 5 months ago
Selected Answer: A
The risk has already been identified. Qualitative Analysis will check the magnitude of the risk on the project.
upvoted 1 times
...
brvndvnwolf
2 years, 5 months ago
Selected Answer: A
A is the correct answer
upvoted 1 times
...
all4one
2 years, 6 months ago
Selected Answer: A
In quantitative analysis, you can identify the risk with the largest impact.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago