During the planning phase, a scheduler uses a WBS as a reference to create a list of activities. The next step of the process is to provide a sequence for all the activities. With which of the following deliverables is the scheduler working?
The deliverable that the scheduler is working on in this scenario is C. Network diagram.
A network diagram is a graphical representation of the logical relationships between activities in a project, showing the dependencies between them. It is typically used to illustrate the sequence of activities in a project, as well as the duration and interdependencies of the activities. To create a network diagram, the scheduler would use a WBS (Work Breakdown Structure) as a reference to identify the activities in the project and then provide a sequence for all the activities by showing the dependencies between them.
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
kmanb
2 years, 3 months agonsjean11203
2 years, 5 months agoBreathHaier
2 years, 3 months agokmanb
2 years, 3 months ago