Question #: 129
Topic #: 1
[All PK0-004 Questions]

A project manager is assigned to an ongoing project. Which of the following is the FIRST document the project manager should review?

  • A. Project schedule
  • B. Action items
  • C. Project charter
  • D. Communication plan
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
SamWiseGam
2 years, 5 months ago
Selected Answer: C
This is almost certainly C. Start by reviewing the project charter. This document will give you a sense of where the project is heading regarding its goals and objectives and the benefits that need to be delivered to the client.
upvoted 2 times
...
HCEYLAN
2 years, 5 months ago
Can anyone explain why the answer is A, Project Schedule?
upvoted 1 times
...
VadimasQ
2 years, 6 months ago
How may the PM know if the schedule even meets project constraints if he doesn't know them?
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel