Is the only one which makes sense "The project manager has rejected numerous candidates", if they are not up to the task they are low-quality resources.
This is an example of resource planning. Resource planning is the process of identifying and acquiring the resources (including personnel, equipment, and materials) that are needed to complete a project. In this case, the project team lacks the necessary team members to complete the project, and the project manager has rejected numerous candidates, indicating that resource planning has not been effectively managed. Proper resource planning is essential for ensuring that a project has the resources it needs to be completed successfully. It is important for project managers to carefully assess the resources required for a project and to identify and acquire the necessary resources in a timely manner in order to avoid delays and disruptions.
The question says it all "The project manager has rejected numerous candidates." this only happens because they are not up to the task.
Also, kmanb seems to be using the AI chat things which is a mess for this. Why is he still here with this? Be careful and know what you are reading and doing, do not blindly trust the answers by anyone.
upvoted 1 times
...
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
BreathHaier
2 years, 3 months agokmanb
2 years, 3 months agoMJVIS
2 years, 4 months agoBreathHaier
2 years, 3 months ago