exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 871 discussion

Actual exam question from CompTIA's PK0-004
Question #: 871
Topic #: 1
[All PK0-004 Questions]

A project manager needs to discuss the team assignment for a new project with the technology director. One of the best developers is needed for a key deliverable; however, the developer is unavailable. Which of the following BEST describes the organizational structure?

  • A. Weak matrix
  • B. Simple organic
  • C. Project oriented
  • D. Strong matrix
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ExamTopicsDiscussor
2 years, 4 months ago
Selected Answer: A
Definitely not B, terrible guide.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago