exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 735 discussion

Actual exam question from CompTIA's PK0-004
Question #: 735
Topic #: 1
[All PK0-004 Questions]

After a change request is approved, a vendor shares the estimated delivery date with project management. A key stakeholder requests to have this change completed by an earlier date. Which of the following is the BEST action for the project manager to take?

  • A. Negotiate with the vendor to complete the change earlier.
  • B. Evaluate the impact of switching tasks on the schedule.
  • C. Consult with the CCB about the request.
  • D. Confront the stakeholder about the unrealistic request.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
kmanb
2 years, 3 months ago
Selected Answer: B
answer is B to me
upvoted 1 times
...
MJVIS
2 years, 4 months ago
Selected Answer: B
Why it's not B: Evaluate the impact of switching tasks on the schedule.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago