An analyst has received the requirements for an internal user dashboard. The analyst confirms the data sources and then creates a wireframe. Which of the following is the NEXT step the analyst should take in the dashboard creation process?
C. Get stakeholder approval is the NEXT step the analyst should take in the dashboard creation process after creating the wireframe. After confirming the data sources and creating a wireframe of the internal user dashboard, it is important to get approval from stakeholders who will be using the dashboard. This includes both internal and external stakeholders, as well as end users who will be accessing the dashboard.
Stakeholder approval is necessary to ensure that the dashboard meets the requirements of the stakeholders, and that it is aligned with the overall goals of the organization. During the approval process, stakeholders may provide feedback or make changes to the wireframe, and the analyst can use this feedback to make any necessary updates to the dashboard design.
Once the stakeholders have provided approval, the analyst can then move forward with deploying the dashboard to production, which involves making the dashboard available to end users and making any final optimizations to ensure that the dashboard is fast, secure, and reliable. This step also involves setting up any necessary subscriptions, so that stakeholders receive regular updates or notifications related to the dashboard.
After creating a wireframe, the next step in the dashboard creation process would typically be to get stakeholder approval. A wireframe is a low-fidelity prototype of the dashboard that shows the layout and structure of the final product, but does not include all of the detailed design elements or functionality. Once the wireframe has been created, it is important to get feedback from stakeholders, such as the internal users who will be using the dashboard, to ensure that the final product meets their needs and expectations. After obtaining stakeholder approval, the analyst can then proceed to the next steps, which might include optimizing the dashboard, creating subscriptions, and deploying to production.
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.DA0-001 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
10cccordrazine
1 year, 11 months ago7380698
11 months, 1 week agoronniehaang
2 years agoronniehaang
2 years agoCineFeX
2 years, 1 month ago