exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 906 discussion

Actual exam question from CompTIA's PK0-004
Question #: 906
Topic #: 1
[All PK0-004 Questions]

Project team members are reporting they have no work after completing a task. Which of the following should the project manager do to ensure the resources are fully utilized?

  • A. Release the team members to the functional manager.
  • B. Sequence tasks based on resource allocation.
  • C. Allocate the unused team members to any open activity.
  • D. Interview each team member for their subject matter expertise.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
kmanb
2 years, 4 months ago
Selected Answer: B
The best thing for the project manager to do in this scenario to ensure that the resources are fully utilized is to sequence tasks based on resource allocation. Resource allocation is the process of assigning the appropriate resources (such as people, equipment, and materials) to specific tasks in a project. By sequencing tasks based on resource allocation, the project manager can ensure that team members are fully utilized and do not have periods of idle time between tasks.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago