A project manager realizes more people are needed to complete a deliverable on time and asks the PMO for more resources. This is an example of:

  • A. shared resources.
  • B. a resource shortage
  • C. interproject resource contention.
  • D. benched resources.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
kmanb
2 years, 4 months ago
Selected Answer: B
This is an example of a resource shortage. A resource shortage occurs when a project lacks the necessary resources (e.g., people, equipment, materials) to complete a particular task or deliverable. In this case, the project manager has recognized that the project does not have enough people to complete the deliverable on time and has asked the PMO for additional resources. This is a common issue that project managers must address in order to ensure that the project stays on track and meets its goals.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago