Exam PK0-004 topic 1 question 870 discussion

Actual exam question from CompTIA's PK0-004
Question #: 870
Topic #: 1
[All PK0-004 Questions]

A critical project team member has fallen ill and must take leave for two weeks. The project manager recognizes this will affect the product release, but the sponsor mandates the product must go live on the date marketing published. Which of the following is the BEST response?

  • A. Tell the project team they need to pick up the extra work to complete the product.
  • B. Tell the testing team to only test what is most critical within the product.
  • C. Reduce the training time for operational staff to support the product.
  • D. Reduce the features being released and produce iterative deliverables later to add features.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
kmanb
2 years, 4 months ago
Selected Answer: D
The best response in this scenario is D. Reduce the features being released and produce iterative deliverables later to add features.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago