Because a feature was not meeting documented requirements, a project milestone was not achieved as scheduled. Which of the following activities should the project manager perform NEXT?
A.
Calculate the schedule variance and update the project status.
B.
Update the project scope and obtain sponsor approval.
C.
Review quality control processes and make the necessary improvements.
D.
Schedule a meeting with stakeholders and update the project objectives.
B. Update the project scope and obtain sponsor approval should be the NEXT activity performed by the project manager because the project milestone was not achieved as scheduled.
When a project milestone is not achieved as planned, it is important for the project manager to determine the root cause of the issue and take appropriate corrective action. In this case, because the feature was not meeting documented requirements, it is likely that the project scope needs to be revised to address the issue. The project manager should update the project scope to reflect the changes that are needed to meet the documented requirements and obtain approval from the sponsor before proceeding with the project.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
kmanb
2 years, 4 months ago