A project with a fixed budget is behind schedule. Immediately after the project due date, resources are allocated to other high-priority projects. Which of the following should the project manager do to complete this project?
A.
Request an increase in funding from the project sponsor.
B.
Obtain resources from a third-party vendor.
C.
Cancel a project that is scheduled to start after this project.
D.
Negotiate the removal of selected deliverables.
Suggested Answer:B🗳️
The project with a fixed budget needs to be completed on time to avoid any financial constraints. On allocation of resources to other high priority projects, the project manager can obtain resources from a third party vendor.
D. Negotiate the removal of selected deliverables is the best option for the project manager to complete this project when the project is behind schedule and resources are allocated to other high-priority projects after the project due date.
When a project is behind schedule and resources are limited, it may not be possible to complete all of the planned deliverables within the original timeframe and budget. In this situation, the project manager may need to negotiate with the stakeholders to determine which deliverables are most critical to the project's success and which can be removed or scaled back in order to meet the project's objectives within the available resources.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
kmanb
2 years, 4 months ago