Two weeks before reaching a major milestone, an unidentified risk is realized. The risk will have a profound effect on the financial health of the project, nearly doubling the actual costs to complete the work. Which of the following is the BEST action for the project manager to consider?

  • A. Meet with the project sponsor and other senior stakeholders to review the risk management plan and determine if the effort should be continued.
  • B. Continue the project work as planned through the upcoming milestone, and then determine the appropriate response.
  • C. Trigger the incident response plan and gather the project participant's opinions on the best way to move forward.
  • D. Implement a full project stop, and then provide the risk information and updated financial metrics to all stakeholders.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
kmanb
2 years, 3 months ago
Selected Answer: A
Should be A I believe
upvoted 2 times
cstan79
2 years, 3 months ago
For once you may be right! Good for you not using chat GPT to answer.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.