During a sprint, the product owner asks the scrum master to work on a quality issue as soon as possible. Which of the following is the scrum master's MOST likely action?
A.
Advise the product owner to submit a change request to the CCB.
B.
Ask the product owner if the issue can be deferred to the next sprint.
C.
Escalate the request by the product owner to upper management.
D.
Inform the product owner of potential delays to the work in the sprint.
The scrum master does not have the authority to escalate requests from the product owner to upper management. Instead, the scrum master's primary role is to help the development team and the product owner to work together effectively to deliver high-quality products. If the product owner asks the scrum master to work on a quality issue as soon as possible, the scrum master's most likely action would be to inform the product owner of potential delays to the work in the sprint and work with the development team and the product owner to find a solution that meets the needs of the project while also following the scrum process.
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
kmanb
2 years, 3 months ago