Actual exam question from CompTIA's PK0-004
Question #: 734
Topic #: 1
[All PK0-004 Questions]

During a project, the project manager realizes some staff positions may be eliminated. Which of the following is the best NEXT step for the project manager to take?

  • A. Communicate the concern with the project sponsor.
  • B. Identify replacement resources.
  • C. Review and update the project schedule.
  • D. Add the risk to the risk register.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MJVIS
2 years, 2 months ago
Selected Answer: D
Add the risk to the risk register. The potential elimination of staff positions is a risk to the project, and therefore, it should be added to the risk register. This will allow the project manager to assess the likelihood and impact of the risk and develop a risk response plan if necessary. Once the risk has been added to the risk register, the project manager may then communicate the concern with the project sponsor, identify replacement resources, and review and update the project schedule as needed.
upvoted 1 times
...
kmanb
2 years, 3 months ago
Selected Answer: A
The best next step for the project manager to take is to communicate the concern with the project sponsor. The project sponsor is responsible for providing the necessary resources and support for the project and should be informed about any potential changes to the project that may impact staffing. The project manager should explain the situation to the project sponsor and discuss the potential impact on the project. Together, they can determine the best course of action and make any necessary adjustments to the project plan. Other steps, such as identifying replacement resources, reviewing and updating the project schedule, and adding the risk to the risk register, may also be necessary, but communicating with the project sponsor should be the first step.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago