Exam PK0-004 topic 1 question 600 discussion

Actual exam question from CompTIA's PK0-004
Question #: 600
Topic #: 1
[All PK0-004 Questions]

Near the end of a sprint, the IT systems were taken down for a critical patch, and the team was inactive for four hours. The team members are concerned they will not be able to complete their tasks before the end of the sprint.
Which of the following BEST describes how the Scrum master should assist the team to finish on time?

  • A. Bring the additional resources to help complete the work.
  • B. Add the uncompleted work to the product backlog.
  • C. Move the work to the next sprint.
  • D. Inform the team members they will need to work longer hours.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
kmanb
2 years, 3 months ago
Selected Answer: B
B. Add the uncompleted work to the product backlog. In Scrum, the product backlog is a prioritized list of work that needs to be completed. If the team is unable to complete their tasks before the end of the sprint due to unforeseen circumstances, the Scrum master should work with the team to add the uncompleted work to the product backlog. This allows the team to prioritize the remaining work and determine how to best allocate their resources to complete it. Adding the uncompleted work to the product backlog also allows the team to reassess the scope of the sprint and determine if it is still realistic given the unexpected downtime. The Scrum master may also need to work with the team to adjust the sprint plan to account for the lost time and ensure that the team is able to deliver a potentially shippable increment of work at the end of the sprint.
upvoted 1 times
BreathHaier
2 years, 3 months ago
!!!!! how the Scrum master should assist the team to finish on time? !!!!! Only A makes this possible. I bet you work for Comptia and doing this to bring down everyone.
upvoted 3 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago