A fire alarm goes off in the building where the project team works. Employees are instructed to leave the premises immediately using the stairs; they are not to use elevators, and they must gather in one place outside the building for further instructions. This is known as a:

  • A. business change response
  • B. change management response
  • C. business continuity response
  • D. risk management response
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
kmanb
2 years, 3 months ago
Selected Answer: C
A business continuity response is a plan that outlines the steps that a company will take to ensure that essential functions can continue during and after a disaster or other interruption. It is not specifically related to risk management, which is the process of identifying, analyzing, and responding to risks that could affect a project, program, or business. However, a business continuity response may be part of the overall risk management plan for an organization.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago