A company has determined it does not have the in-house capability to perform a project and wants to procure third-party services. Which of the following documents will the company MOST likely release FIRST?
Request for Information (RFI) An RFI is used when you need to gather more
information about the goods or services you need to procure. This process will give you a
sense for the number of providers or contractors who can provide the goods or services,
and you will get an idea of cost. An RFI or RFQ is used when the costs are unknown to
you and you need an estimate for the goods or services.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
sedative
2 years, 2 months ago