Refer to the exhibit.
An installer is adding a new 10 GbE array and switches into an existing 1 GbE environment. The existing 1 GbE switches are stacked. The installer needs to choose an uplink method.
Which uplink method should the installer choose?

  • A. Chain
  • B. Closed Loop
  • C. Straight uplink
  • D. Split uplink
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️
When integrating 10Gb switches into existing 1Gb switching environment, how the mixed speed switches are interconnected (split vs. straight uplink) does not have a significant impact on performance as long as the uplinks are sized appropriately to your workloads.
If 1Gb switches are configured as a stack then use the split interconnect pattern.
If 1Gb switches are not stacked, then use the straight interconnect pattern.
References: Dell PS Series Configuration Guide, page 59
http://en.community.dell.com/dell-groups/dtcmedia/m/mediagallery/19852516/download

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...