Exam 712-50 topic 1 question 101 discussion

Actual exam question from ECCouncil's 712-50
Question #: 101
Topic #: 1
[All 712-50 Questions]

Which of the following activities results in change requests?

  • A. Corrective actions
  • B. Defect repair
  • C. Preventive actions
  • D. Inspection
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
musagul
2 months, 2 weeks ago
Selected Answer: C
You must create a change request when you are doing preventive action. Because the "preventive action" can prevent legal business processes. C is Correct.
upvoted 1 times
...
MJ_Sr
4 months, 2 weeks ago
This should actually be "B". A defect repair results in a change request ticket. Corrective actions would happen after and preventive actions happen before.
upvoted 1 times
...
RC2073
8 months ago
Selected Answer: C
C is correct per other Q&A sites online
upvoted 1 times
...
kaibutsu
9 months ago
I think we need more context. I can see A or C. If it said "Emergency Change" then I would say "Corrective."
upvoted 2 times
...
Jesse572
9 months, 4 weeks ago
Selected Answer: A
We know Inspection is not it for sure. Defect repair create work orders to repair / replace items. Preventive actions are already implemented and prevent users / systems from performing specific functions. I would have to state the answer is Corrective Actions.
upvoted 1 times
...
arifbhatkar
10 months ago
A. Corrective actions Corrective actions involve addressing identified issues or problems within a system or process to prevent their recurrence. When corrective actions are implemented, they often require change requests to modify the existing system or process. These change requests capture the necessary modifications or updates needed to rectify the identified issues and improve the overall performance or functionality. Therefore, corrective actions typically lead to change requests as part of the process for implementing the necessary changes.
upvoted 2 times
...
VOAKDO_cciso
11 months ago
Selected Answer: C
corrective=after a problem happens . preventive=before a problem happens . Here, it does not say when,...., it supposes before
upvoted 1 times
...
Examal
12 months ago
A, Preventive actions may not alter any changes or even may the require any reboots or resets.
upvoted 1 times
...
Pika26
1 year, 1 month ago
Answer should be A, corrective actions. Corrective actions are activities taken to address identified problems, issues, or defects that have occurred during the project execution. These activities may result in change requests, which are formal proposals to modify any project document, deliverable, or baseline.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...