Which of the following activities results in change requests?

  • A. Corrective actions
  • B. Defect repair
  • C. Preventive actions
  • D. Inspection
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Pika26
1 day, 7 hours ago
Answer should be A, corrective actions. Corrective actions are activities taken to address identified problems, issues, or defects that have occurred during the project execution. These activities may result in change requests, which are formal proposals to modify any project document, deliverable, or baseline.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...