A. Answer A
Please review : https://www.prince2.com/uk/blog/projects-programmes-and-portfolios-whats-the-difference
Individual projects are typically monitored and managed at the program level. A program consists of multiple related projects that are managed and coordinated together to achieve broader organizational objectives. The program level ensures that the projects are aligned and are contributing to the overall goals effectively
Portfolio: Refers to the collection of programs and projects aligned with strategic objectives, but it focuses on overall prioritization and resource allocation, not on managing individual projects directly
The correct answer is A. Program.
At the program level of governance, individual projects are monitored and managed. A program is a collection of related projects that are coordinated and managed together to achieve specific strategic objectives. It provides oversight and guidance to the individual projects within the program.
This section is not available anymore. Please use the main Exam Page.712-50 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Bettoxicity
4 months, 3 weeks agoValen2259
8 months, 1 week agonshams
10 months, 4 weeks agoMeav
1 year agoarifbhatkar
1 year, 11 months agoPika26
2 years, 2 months ago