What is the correct sequence of steps involved in scheduling a threat intelligence program?
1. Review the project charter
2. Identify all deliverables
3. Identify the sequence of activities
4. Identify task dependencies
5. Develop the final schedule
6. Estimate duration of each activity
7. Identify and estimate resources for all activities
8. Define all activities
9. Build a work breakdown structure (WBS)

  • A. 1-->9-->2-->8-->3-->7-->4-->6-->5
  • B. 3-->4-->5-->2-->1-->9-->8-->7-->6
  • C. 1-->2-->3-->4-->5-->6-->9-->8-->7
  • D. 1-->2-->3-->4-->5-->6-->7-->8-->9
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
BionicBeaver
10 months, 4 weeks ago
Selected Answer: A
Answer is A As per Module 03 Page 182 of CTIA Courseware
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...