A recovery point objective (RPO) is the maximum time frame for which an organization loses data after a major IT outage. It determines the acceptable amount of data loss an enterprise can suffer in case of a disruption.
RTO (the Recovery Time Objective), is a metric that defines the time to recover your IT infrastructure and services following a disaster to ensure business continuity.
Recovery point objective (RPO) is the maximum time frame for which an organization loses data after a major IT outage
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.312-38 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
maaax
Highly Voted 3 years, 2 months ago5ed93df
Most Recent 8 months, 3 weeks agoethacker
2 years agocastro_siya
2 years, 1 month agosadsad
2 years, 4 months agoalvaroestebancta
3 years, 7 months agoui
4 years, 1 month ago