Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam ASF topic 1 question 62 discussion

Actual exam question from Exin's ASF
Question #: 62
Topic #: 1
[All ASF Questions]

Who is accountable for a task that is assigned to a single Team member?

  • A. The Product Owner
  • B. The Scrum Master
  • C. The Development Team
  • D. The single Team member
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
james2033
6 months, 2 weeks ago
Selected Answer: C
Development team.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...