Which information from the risk register is used during the 'assess - evaluate' step to calculate the total risk exposure of an activity?

  • A. Identified risks resulting from a risk response action
  • B. Estimated likelihood of the risks occurring
  • C. Exposure of the risks after completion of risk responses
  • D. The timeframe in which the risks are likely to occur
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...